| DATE | ACTIVITY |
| 11/11/2009 |
COPE notified of unofficial BOE report that includes lack of Conceptual Framework for Advanced Programs. Minutes |
| 1/14/2010 |
BOE Report Received |
| 1/28/2010 |
COPE notified of new areas of improvement cited by NCATE. Minutes |
| 2/4/2010 |
Conceptual Framework Task Force Formed, Membership |
| 2/23/2010 |
COPE notified of possible Focus Visit. Minutes |
| 3/19/2010 |
Conceptual Framework Task Force, Initial Meeting, Task Force received charge from Head of the Unit. Charge |
| 4/2/2010 |
Conceptual Framework Task Force Working Session, Documents developed. |
| 4/30/2010 |
Head of Unit communicates with PEF concerning AFI. Email |
| 5/5/2010 |
Conceptual Framework Task Force Working Session, Template presented, Draft Document developed. |
| 5/14/2010 |
Subcommittee of Task Force composes introduction to Conceptual Framework. Updated Draft document sent to Task Force. Draft Document sent to program directors who are asked to review the document and submit reference lists. Email with Draft |
| 6/3/2010 | Conceptual Framework Task Force Working Session, Draft Document further developed. Draft |
| 6/29/2010 |
Conceptual Framework received by COPE, Input requested. Minutes |
| 7/2/2010 |
Input received by Task Force, Suggestions |
| 7/23/2010 |
NCATE Focus Visit Steering Committee Revised Conceptual Framework based on suggestions, Document. |
| 9/9/2010 |
Conceptual Framework presented to PEF Agenda |
| 9/24/2010 |
Meeting with Dr. Kim Boyd, Standard 2 consultant |
| 1/4/2011 |
Meeting with Dr. Kim Boyd, Standard 2 consultant |
| 1/7/2011 | ERZ Advisory Council received Conceptual Framework, input requested Minutes |
| 2/22/2011 |
Conceptual Framework approved by COPE Minutes |